Let the work begin! 14.04.
The construction crane is delivered 14.04.
The dining room is cleared out 14.04.
Our Edi also pitches in! 14.04.
Our team clears everything out – you probably recognize one or two of them! 14.04.

The crane stands! 14.04.
The wooden terrace is transported away 15.04.
The new cellar has almost been excavated out 19.04.
Our garage got a little smaller, too! 19.04.
A beautiful day for building! 20.04.
Our owner’s workplace – only the shelf for glasses is missing! 20.04.
The backhoe in the "old" restaurant! 20.04.
The first concrete starts being laid! 20.04.
And naturally, Paul is also busy on the construction site! 23.04.
The construction sign for Naturhotel Tandler set against magnificent mountain scenery! 24.04.
The cellar walls are done 26.04.

Ca. 20 of these steel girders are installed to support the structure 26.04.
Installation of a steel girder 26.04.
Standing in the entrance to the former dining room! 26.04.
Not much left of the old rooms 29.04.
A small section of the roof is already missing 29.04.
We also need a new spot for our emergency back-up generator 29.04.
The old room furnishings are removed 30.04.
One of our former armoires 30.04.
This is where we are building the lift 06.05.
Laying the brickwork for the lift begins 06.05.

The exterior wall of the new restaurant area 06.05.
The roof tiles are removed 10.05.
Now it’s the roof’s turn 10.05.
2 of our hard-working construction workers during demolition 10.05.
With the help of a crane, the old roof is removed 10.05
Work continues on every floor 10.05.
Soon the roof will be gone 10.05.
View from the top floor of the new terrace and restaurant 10.05.
The last wooden beams are pulled out 10.05.
The exterior walls of the top floor are chiseled off 10.05.
Topless 12.05.
Some of the construction material which has already been torn out 12.05.
The upper part is tarred for added protection 12.05.
For further construction, a scaffold was erected 17.05.
Some of the rooms are already being divided up 18.05.
Concrete is being poured for ceiling of the new restaurant and the lounge 19.05.
Here we are building the exterior walls of the 3rd floor 19.05.
Two men with major responsibilities – foreman, Michl, and crane drive, Rudi 19.05.
No words necessary! 19.05.
Concrete comes through the ceiling 20.05.
The wood construction of the old restaurant is revealed 20.05.
The lift shaft and stairway have reached the next floor 27.05.
The walls of the 3rd floor are finished 27.05.
The fireplace for the next wood stove in the lounge 27.05.
The rain comes! Everything is covered – though it doesn’t stay completely dry 27.05.
Concrete is poured for the ceiling of the 3rd floor 28.05.

We begin removing the construction materials which had been torn out 28.05.
The 2nd-floor balcony gets a facelift as well 02.06.
The top floor gets its brick walls 02.06.
The elevator shaft and stairway have now reached the 4th floor 02.06
Wood for the roof is delivered 09.06.

The men on the roof are ready to go 09.06.
And things get going 09.06.
The east side already looks good 09.06.
And tomorrow continues on the west side 09.06.
South side 11.06.
North side 11.06.
Peter and Schorsch working 11.06.
Men who take on everything and keep the building site clean 11.06.
Roof with panoramic view 11.06
View from the new 4th-floor relaxation room 11.06.

View of the new Finnish sauna 11.06.
Painter adding a few finishing touches. Just 5 days and the restaurant reopens 11.06.
The restaurant has reopened 16.06.
The counter in all its renewed glory 16.06.
Our first guests enjoying coffee and cake 16.06.
The roof is on 16.06.
Just 1 floor and the shell construction is complete – unfortunately, the weather has been slowing things down for days in a row 16.06.
Now the ridge pole has also been installed on the roof 20.06.

The last ceiling and rooftop terrace in the sauna area are being concreted 23.06.

Fascia boards are being installed 28.06.
The last garage gets torn down ....29.06.

...and transported away 29.06.
The shell is finished 29.06.
Rudi, our crane driver, has a handle on everything – he also got a little color 29.06.
The ground tank is buried 05.07.
Edi - our pump master 05.07.
The tank is embedded in sand 05.07.
Done – the ground tank is buried and the view of the valley is unobstructed again 06.07.
The construction company is finished. The last items are transported away 07.07.
The construction crane is dismantled after about 2 1/2 months ... 08.07.
... and now heads for another construction site 08.07.
The construction company’s last container is removed 09.07.
View from “Tree” room 15.07.
View from “Alpine tarn” room 15.07.
View from “Mountain” room 15.07.
View from the bathtub in the “Mountain” room 15.07.
The windows are delivered 15.07.
We begin to install the windows 19.07.
The foreman as windows are installed, with view of the old farms 20.07.
The plaster brigade has also begun to work – the walls in the quiet room already look very clean 20.07.
The carpenters have already installed 3 floors of windows 22.07.
So now we’re safe, even if there’s a summer thunderstorm - HOPEFULLY 22.07.
The plasterers have completed 2 floors 22.07.
The electric and water lines crisscross each other throughout the house 26.07.
Reini is responsible for ensuring that everything electrical functions correctly by the beginning of December 26.07.
The projecting roof on the rooftop terrace is installed 27.07.

Now all of the balconies are roofed, so that regardless of time of day or weather, guests can always go outside 29.07.
We are curious to see how everything works 04.08.
Roofing tar for the rooftop terrace 04.08.
Panoramic window from the sauna area to the relaxation room 05.08.
The scaffolding for the exterior insulation is assembled 08.08.
This is what it looks like with the flooring removed 10.08.
Just one day later and things are getting a little tidier 11.08.
This piping helps recycle heat from the saunas 11.08.
This is used in the new relaxation room of the Alpinarium 11.08.
Our spackler is already hard at work, too – view of the wall in the sauna area 11.08.
In the new lounge, the walls and ceiling are already plastered 11.08.
The buffet room is currently being used as storage space 11.08.
The owner in her element – looking after the trees 11.08.
The balcony exits have already been installed 16.08.
Now we‘re beginning to lay the impact-noise mats 17.08.
And after that comes the under-floor heating 19.08.
Ca. 9 km are laid in the Naturhotel 19.08.
Now the hotel is already to begin with the exterior insulation work 19.08.
The 14 cm-thick exterior insulation is installed 23.08.
The stone flooring is complete on the first floor 23.08.

With all the stone floors complete – in a few days the tile-layers and painters can get started 27.08.
The insulation installers are also making good progress 30.08.
To avoid cold spots, the balcony exits are also well insulated 30.08.
The guest elevator is delivered ... 30.08.
... and installation begins 31.08.
At the Brunnalm it has already been snowing, which means we need to hurry 31.08.
At the annex, too, insulation can be installed before the building is clad with larch 31.08.
over this comes a protective sheet, preventing the insulation from getting damp 01.09.
Late summer in Defereggental at its most beautiful 01.09.
Das Weisse Beil – quite a sight 01.09.
The elevator tower is now well boxed in 01.09.
The painters begin their work 02.09.

Larch boards... 02.09.
... which are being installed as the outer façade for the annex 02.09.
Fuse boxes are installed on each floor 03.09.
Some of the hallways are already white 03.09.
The bathtubs have been delivered and will be installed in the next few days 03.09.
The elevator cabin is assembled by the technicians 06.09.
The motor has already been installed as well 06.09.
Here’s where it will go up and down 06.09.
To reinforce the roof overhang, additional iron girders are installed 06.09.
Our carpenters are also making good progress on the larch façade 06.09.
materials are being delivered on all sides 06.09.
The lift doors have also been installed 08.09.
Wall tiles are being delivered... 08.09.
... and brought up to each of the floors 08.09.
The first bathtub is already fitted 08.09.
The tile-layers begin their work. Here’s what the wall tiles for our new bathrooms and WC’s look like 09.09.
The façade on the west side is as good as finished 09.09.
The tiled walls and the bathtub in the bathroom of a “Mountain” category room 17.09.
Here’s where we are installing a big mirror with lighting and a double washbasin 17.09.
The façade on the annex is ready. Now we can make preparations to insulate and add the façade to the main building 17.09.
The window elements for the panorama room are delivered ... 23.09.
... and raised to the 4th floor 23.09.
View of the new aroma steam bath 23.09.
The larch façade is ready 25.09.
View from the scenic terrace across the snow-covered Defereggental 25.09.
Some more digging is necessary... 01.10.
...in order to connect the new electric lines 01.10.
Naturhotel Tandler – the logo is ready 01.10.
The scaffolding is pulled down 01.10.
The facade on the north side is also finished 01.10.
Now the carpenters can begin with the balconies 01.10.
The natural slate flooring in the bathrooms 01.10.
The wood flooring in the rooms is laid 07.10.
View of the east side of our new Naturhotel Tandler 07.10.
The first room is fitted out 14.10.

The sauna is already complete 14.10
The lift entrance is clad with wood 20.10.
On the 4th floor, the entire side up to the roof is clad in spruce 20.10
A glass fence was installed on the panorama terrace 20.10.
Guaranteeing unrestricted view of the glorious countryside of our valley 20.10
The sauna cabins are also clad in wood 20.10.
Our sample room is ready 20.10.
Coat rack 20.10.
Bed 20.10.
Desk 20.10.
Shower fixtures are already installed 20.10.
What an amazing autumn day – fresh snow, sun and blue skies 26.10.
What more could a skier’s heart desire 26.10.
The first snow on our new roofs 26.10.
The fireplace for the lounge is being installed 02.11.
Here’s how the interior doors look 03.11.
The carpenters begin to install the balconies 03.11.